Sample Design: White sturgeon fisheries management planning for Bonneville, The Dalles, and John Day reservoi - Oregon Department of Fish and Wildlife
- ID: 6821
- State: Finalized
- Owner: Christine Mallette
- Collaborator(s): Blaine Parker, Brad James, Jen Bayer, Peter Stevens, Tim Counihan, Tom Rien, Tucker Jones
- Spatial Design Category: Other
- Sites in Design: 1
- Has Location Privacy: No
- Data Repository: ODFW Columbia Fisheries Program website (See Sample Design Overview for full list)
- Created by: Christine Mallette
- Created: 12/5/2017
- Updated by:
- Updated:
- Version History: v1.0 Finalized (12/5/2017)
The details of this Sample Design, including all the parameters used to generate it, are included below. Sample designs must belong to a Study Plan.
Description
<none>
Start Year
2006
End Year
2009
Study Plan
Population Status Monitoring in Bonneville, The Dalles and John Day reservoirs (1986-050-00) v1.0
Data Repositories
- ODFW Columbia Fisheries Program website
- Oregon Department of Fish and Wildlife website
- PTAGIS Website
- ODFW's Data Clearinghouse
- ODFW Sturgeon Database
Focal Species
<none>
Photos
<none>
Documents
<none>
Area of Inference
| Mainstem Reaches and Dams: | Little Goose Dam to Lower Granite Dam |
| Mainstem Reaches and Dams: | Lower Monumental Dam to Little Goose Dam |
| Mainstem Reaches and Dams: | Bonneville Dam to The Dalles Dam |
| Mainstem Reaches and Dams: | Ice Harbor Dam to Lower Monumental Dam |
| Mainstem Reaches and Dams: | John Day Dam to McNary Dam |
| Mainstem Reaches and Dams: | McNary Dam to Confluence of Snake and Columbia River |
| NPPC Subbasins: | SNAKE LOWER |
| Mainstem Reaches and Dams: | The Dalles Dam to John Day Dam |
AOI Notes
Columbia River - Bonneville to Priest Rapids Dam and Snake River to Lower Granite Dam
Sample Sites
These are the unique sites that are participating in this sample design over the time period covered by the design.
Sampling Schedule
This section describes which sites are scheduled to be sampled in any given year, and (if applicable) the panel and stratum that the sample site belongs to.
Plan Description
<none>
WorkStatementElements Referencing This Design
- Project: 1986-050-00, Contract: 50318, Work Statement Element: Work Element S: 162 - White sturgeon fisheries management planning for Bonneville, The Dalles, and John Day reservoi
- Project: 1986-050-00, Contract: 50318, Work Statement Element: Work Element V: 162 - Reservoir specific white sturgeon stock assessment data summary and analysis
- Project: 1986-050-00, Contract: 59559, Work Statement Element: Work Element E: 162 - White sturgeon fisheries management planning for Bonneville, The Dalles, and John Day reservoi
- Project: 1986-050-00, Contract: 59559, Work Statement Element: Work Element H: 162 - The Dalles and John Day reservoirs white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: CR-201277, Work Statement Element: Work Element H: 162 - Reservoir specific white sturgeon stock assessment data summary and analysis
- Project: 1986-050-00, Contract: CR-201277, Work Statement Element: Work Element E: 162 - White sturgeon fisheries management planning for Bonneville, The Dalles, and John Day reservoi
- Project: 1986-050-00, Contract: 63186, Work Statement Element: Work Element E: 162 - Use population assessments to plan for fishery management activities in BON, TDA, and JDA
- Project: 1986-050-00, Contract: 63186, Work Statement Element: Work Element H: 162 - John Day and The Dalles reservoirs white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: 66928, Work Statement Element: Work Element E: 162 - Use population assessments to plan for fishery management activities in BON, TDA, and JDA
- Project: 1986-050-00, Contract: 66928, Work Statement Element: Work Element H: 162 - The Dalles and Bonneville reservoirs white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: 70076, Work Statement Element: Work Element E: 162 - Use population assessments to plan for fishery management activities in BON, TDA, and JDA
- Project: 1986-050-00, Contract: 70076, Work Statement Element: Work Element H: 162 - Bonneville and John Day reservoirs white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: 73881, Work Statement Element: Work Element F: 162 - Use population assessments to plan for fishery management activities in BON, TDA, and JDA
- Project: 1986-050-00, Contract: 73881, Work Statement Element: Work Element I: 162 - John Day and The Dalles reservoirs white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: 74313 REL 10, Work Statement Element: Work Element F: 162 - Use population assessments to plan for fishery management activities in BON, TDA, and JDA
- Project: 1986-050-00, Contract: 74313 REL 10, Work Statement Element: Work Element I: 162 - The Dalles reservoir white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: 74313 REL 10, Work Statement Element: Work Element O: 162 - Ice Harbor, Lower Monumental, and Little Goose reservoirs white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: 74313 REL 10, Work Statement Element: Work Element Q: 162 - White sturgeon: assessment of spawning habitat and use in the John Day reservoir
- Project: 1986-050-00, Contract: 39233, Work Statement Element: Work Element F: 157 - Bonneville Reservoir white sturgeon stock assessment sampling
- Project: 1986-050-00, Contract: 24751, Work Statement Element: Work Element F: 157 - Bonneville Reservoir white sturgeon stock assessment sampling
- Project: 1986-050-00, Contract: 74313 REL 33, Work Statement Element: Work Element F: 162 - Use population assessments to plan for fishery management activities in BON, TDA, and JDA
- Project: 1986-050-00, Contract: 74313 REL 33, Work Statement Element: Work Element I: 162 - Bonneville reservoir white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: 74313 REL 33, Work Statement Element: Work Element O: 162 - Ice Harbor, Lower Monumental, and Little Goose reservoirs white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: 74313 REL 33, Work Statement Element: Work Element Q: 162 - White sturgeon: assessment of spawning habitat and use in the John Day reservoir
- Project: 1986-050-00, Contract: 74313 REL 60, Work Statement Element: Work Element F: 162 - Use population assessments to plan for fishery management activities in BON, TDA, and JDA
- Project: 1986-050-00, Contract: 74313 REL 60, Work Statement Element: Work Element I: 162 - John Day reservoir white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: 74313 REL 81, Work Statement Element: Work Element F: 162 - Use population assessments to plan for fishery management activities in BON, TDA, and JDA
- Project: 1986-050-00, Contract: 74313 REL 81, Work Statement Element: Work Element I: 162 - The Dalles reservoir white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: 74313 REL 103, Work Statement Element: Work Element F: 162 - Use population assessments to plan for fishery management activities in BON, TDA, and JDA
- Project: 1986-050-00, Contract: 74313 REL 103, Work Statement Element: Work Element I: 162 - Bonneville reservoir white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: 84041 REL 7, Work Statement Element: Work Element F: 162 - Use population assessments to plan for fishery management activities in BON, TDA, and JDA
- Project: 1986-050-00, Contract: 84041 REL 7, Work Statement Element: Work Element I: 162 - Bonneville reservoir white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: 84041 REL 25, Work Statement Element: Work Element F: 162 - Use population assessments to plan for fishery management activities in BON, TDA, and JDA
- Project: 1986-050-00, Contract: 84041 REL 25, Work Statement Element: Work Element I: 162 - The Dalles reservoir white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: 84041 REL 39, Work Statement Element: Work Element F: 162 - Use population assessments to plan for fishery management activities in BON, TDA, and JDA
- Project: 1986-050-00, Contract: 84041 REL 39, Work Statement Element: Work Element I: 162 - Bonneville reservoir white sturgeon stock assessment data summary and analyses
- Project: 1986-050-00, Contract: 84041 REL 59, Work Statement Element: Work Element F: 162 - Use population assessments to plan for fishery management activities in BON, TDA, and JDA
- Project: 1986-050-00, Contract: 84041 REL 59, Work Statement Element: Work Element I: 162 - John Day reservoir white sturgeon stock assessment data summary and analyses